Home > Storage > PowerStore > Storage Admin > Dell PowerStore Manager Overview > Migration: Imports
After an import is successfully initiated, the import session displays under Migration > Import External Storage > Block Imports or File Imports (Figure 39). This page allows you to manage the import sessions as required including the following supported operations: Cancel, Cutover, Enable Destination Volume, Start Copy, Pause, Resume, and Cleanup. During an ongoing import, a cancel operation enables you to change the active path to the source storage resource. When a cutover operation is performed, the import session can no longer be canceled.
Table 5 shows the actions available for import sessions along with the associated descriptions. An action depends on the import job current state.
Action | Overview |
Cancel |
|
Cutover |
Note: After a cutover has been completed, it cannot be canceled, and it is not possible to revert to the source resource. |
Pause |
|
Resume |
|
Cleanup |
|
Actions applicable to Agentless Import | |
Enable Destination Volume | Note: Before you select this action, ensure the host application accessing the source volume or volumes is shut down. Also, ensure the host mappings are removed from the volume or volumes in the source system.
For each import session that is in the Ready To Enable Destination Volume state, select the import session, and select Import Actions > Enable Destination Volume to progress each import session to the Ready to Start Copy state. |
Start Copy | Note: Ensure the host application has been reconfigured to access and use the destination volume or volumes in PowerStore.
For each import session that is in the Ready to Start Copy state, select the import session, and select Import Actions > Start Copy to progress each import session to the Copy In Progress state |