The following table lists the power drops required for each number of SUs.
Number of SU nodes | Required number of power drops | ||
Single phase | Three-phase Delta | Three-phase Wye | |
Dense | |||
4 | 2 | 1 | 1 |
8 | 3 | 1 | 1 |
12 | 4 | 2 | 1 |
16 | 5 | 3 | 2 |
Hybrid | |||
4 | 2 | 2 | 2 |
8 | 4 | 2 | 2 |
12 | 6 | 2 | 2 |
16 | 8 | 4 | 2 |
All flash | |||
4 | 2 | 2 | 2 |
8 | 4 | 2 | 2 |
12 | 4-6 * | 2 | 2 |
16 | 6-8 * | 2-4 * | 2 |
* You need a higher number of power drops if you order these nodes with Intel Xeon 6248R processors.
The integrated system enables you to use different PDU connector types to best integrate into your data center, as listed in the following table.
Location | Single phase | Three-phase Delta | Three-phase Wye |
North America, Japan | L630P L7-30P Russellstoll 3750DP | Hubbell Pro CS8365L Russellstoll 9P54U2T/1100 | Hubbell C530P6S ABL Sursum S52S0A Flying Leads |
International | IEC60309-332P6W | Russellstoll 9P54U2T/1100 | Hubbell C530P6S ABL Sursum S52S30A Flying Leads |
Australia | Clipsal 56PA332 |