Ensure that Ethernet interfaces that are connected to PowerFlex nodes and switches are up, and are at the expected speed and MTU. Port channels connected to PowerFlex nodes may show up on one leaf in the pair, but are down with the reason lacp-fail
on the other leaf since the nodes are not yet deployed. After PowerFlex nodes are deployed, the applicable port channels should be up on both leaf switches.
Leaf1A# show interface status
-----------------------------------------------------------------------------
Name Description Oper Reason AutoNeg Speed MTU
-----------------------------------------------------------------------------
Eth1/1 To SO node NIC0:1 up oper-up off 25000 9216
Eth1/2 To SO node NIC0:1 up oper-up off 25000 9216
(output truncated)
Eth1/47 Link to external network up oper-up off 25000 9216
Eth1/48 Link to external network up oper-up off 25000 9216
Eth1/49 Peer link to Leaf 1B up oper-up off 100000 9216
Eth1/50 Peer link to Leaf 1B up oper-up off 100000 9216
Eth1/51 Peer link to Leaf 1B up oper-up off 100000 9216
Eth1/52 Peer link to Leaf 1B up oper-up off 100000 9216
Eth1/53 To Spine1 up oper-up off 100000 9216
Eth1/54 To Spine2 up oper-up off 100000 9216
Eth1/55 To Spine3 up oper-up off 100000 9216
Eth1/56 To Spine4 up oper-up off 100000 9216
PortChannel1 Bond0 to SO node down lacp-fail - 25000 9216
PortChannel2 Bond0 to SO node down lacp-fail - 25000 9216
(output truncated)
PortChannel100 MCLAG peer link up oper-up - 400000 9216